List of questions
Related questions
Question 16 - PMI-ACP discussion
During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good.
What should the agile team lead do?
A.
Require the team to try only those ideas that will ensure success.
B.
Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.
C.
Associate idea successes and failures with the team's incentive plan to ensure accountability.
D.
Encourage the team to try the ideas, even if failure may be the outcome.
Your answer:
0 comments
Sorted by
Leave a comment first