Question 18 - PMI-ACP discussion
An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated.
What should the agile practitioner do?
A.
Foster stronger communication by hosting cross-organizational meetings between the two teams.
B.
Suggest merging the teams to avoid misunderstandings.
C.
Create stories from full technical specifications to avoid ambiguity.
D.
Co-locate the teams to encourage osmotic communication.