An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables; however, issues arise when the deliverables are integrated.

What should the agile practitioner do?

A.
Foster stronger communication by hosting cross-organizational meetings between the two teams.
Answers
A.
Foster stronger communication by hosting cross-organizational meetings between the two teams.
B.
Suggest merging the teams to avoid misunderstandings.
Answers
B.
Suggest merging the teams to avoid misunderstandings.
C.
Create stories from full technical specifications to avoid ambiguity.
Answers
C.
Create stories from full technical specifications to avoid ambiguity.
D.
Co-locate the teams to encourage osmotic communication.
Answers
D.
Co-locate the teams to encourage osmotic communication.
Suggested answer: A