Question 19 - PMI-ACP discussion
There is a database feature requiring three members of a seven person team. A meeting is scheduled at the beginning of the sprint to go over technical needs to complete the story.
Who should the Scrum Master invite to the meeting?
A.
The core team and the customer
B.
The product owner and key stakeholders
C.
The customer and the sponsor
D.
The core team and the product owner