Question 20 - PMI-ACP discussion

Report
Export

Midway through a sprint, a team member discovers that the product design fails to adhere to the organization's enterprise architecture standards. Since this required escalation to the architecture team for further analysis and resolution, the team was unable to deliver its sprint goal and the sprint was cancelled.

What should the team have done to avoid this?

A.
Escalated the issue to management
Answers
A.
Escalated the issue to management
B.
Ensured the early engagement of key stakeholders
Answers
B.
Ensured the early engagement of key stakeholders
C.
Provided feedback to the architecture team to change the enterprise architecture standards
Answers
C.
Provided feedback to the architecture team to change the enterprise architecture standards
D.
Raised an exception for non-adherence to the enterprise architecture standards for this product
Answers
D.
Raised an exception for non-adherence to the enterprise architecture standards for this product
Suggested answer: B