What should the agile practitioner know about tracking velocity?

A.
A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.
Answers
A.
A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.
B.
A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.
Answers
B.
A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.
C.
A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.
Answers
C.
A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.
D.
A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.
Answers
D.
A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.
Suggested answer: C