Question 38 - PMI-ACP discussion
After seeing the planned features for an upcoming release, a customer notes that a vitally important and complex one is missing. The team estimates that this feature significantly exceeds its average velocity.
How can this issue be resolved?
A.
Break down the feature into smaller parts, and commit to completing the minimum viable product.
B.
Complete the iteration to which they have already committed, and include the feature in the next release.
C.
Change the planned features to include only the vitally important one.
D.
Extend the iteration to complete the feature.