Business stakeholders of an agile project frequently skip the review meetings. What should the agile practitioner do?

A.
Ask the product owner to inform all stakeholders about the project's progress.
Answers
A.
Ask the product owner to inform all stakeholders about the project's progress.
B.
Send meeting notes to all stakeholders after each review meeting.
Answers
B.
Send meeting notes to all stakeholders after each review meeting.
C.
Include the results of the review meetings in the information radiators.
Answers
C.
Include the results of the review meetings in the information radiators.
D.
Convince the stakeholders of the benefits of attending the review meetings.
Answers
D.
Convince the stakeholders of the benefits of attending the review meetings.
Suggested answer: D