ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 43 - PMI-ACP discussion

Report
Export

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.

What should the project leader do?

A.
Encourage the team to self-organize and determine how to best complete their existing work and this spike.
Answers
A.
Encourage the team to self-organize and determine how to best complete their existing work and this spike.
B.
Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.
Answers
B.
Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.
C.
Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.
Answers
C.
Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.
D.
Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.
Answers
D.
Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.
Suggested answer: A
asked 23/09/2024
Shivanth Jha
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first