Question 45 - PMI-ACP discussion
After three iterations, it is identified that a project's underlying security structure architecture is unstable. While there is a technical solution, all work to date is flawed. This will impact several future business service offerings.
What should the product owner do to resolve this?
A.
Ask the development team to address the issue since it is in their domain.
B.
Review the project's risk matrix, and follow the steps outlined in the risk mitigation plan.
C.
Meet with the team and stakeholders to address rework and rewrite stories as needed.
D.
Cancel the current sprint, and meet with stakeholders to reassess the project's validity.
Your answer: