Question 46 - PMI-ACP discussion

Report
Export

A project team identifies a number of technical challenges with features in the next sprint. What should they do?

A.
Request direction from the technical manager.
Answers
A.
Request direction from the technical manager.
B.
Encourage the product owner to reallocate the features to another sprint.
Answers
B.
Encourage the product owner to reallocate the features to another sprint.
C.
Determine who is best qualified to address the challenges.
Answers
C.
Determine who is best qualified to address the challenges.
D.
Ask the product owner to assign the tasks to the most appropriately skilled resources.
Answers
D.
Ask the product owner to assign the tasks to the most appropriately skilled resources.
Suggested answer: C
asked 23/09/2024
CCF AG Alexander Seidler