Question 46 - PMI-ACP discussion
A project team identifies a number of technical challenges with features in the next sprint. What should they do?
A.
Request direction from the technical manager.
B.
Encourage the product owner to reallocate the features to another sprint.
C.
Determine who is best qualified to address the challenges.
D.
Ask the product owner to assign the tasks to the most appropriately skilled resources.
Your answer: