List of questions
Related questions
Question 54 - PMI-ACP discussion
At the retrospective, the burndown chart shows that the project is slightly behind schedule. The project team identifies an inexperienced software engineer as the source of reduced velocity-How should the project team address this issue?
A.
Suggest pair programming during the retrospective.
B.
Ask the product owner to re-prioritize the user stories at the next retrospective.
C.
Re-estimate the story points with team members at the next iteration planning meeting.
D.
Assign less complex user stories to the inexperienced software engineer at the next iteration planning meeting.
Your answer:
0 comments
Sorted by
Leave a comment first