Question 55 - PMI-ACP discussion

Report
Export

A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.

What steps should the project leader take to improve knowledge sharing?

A.
Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.
Answers
A.
Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.
B.
Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.
Answers
B.
Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.
C.
Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.
Answers
C.
Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.
D.
Inform the customer of the challenges and lower velocity of the project to accomodate for the slower delivery pace.
Answers
D.
Inform the customer of the challenges and lower velocity of the project to accomodate for the slower delivery pace.
Suggested answer: B