During a sprint, the team encounters a technical problem that becomes an impediment to completing two stories. What should the scrum master do?

A.
Ask the lead developer to identify a solution, and then share the details with the team.
Answers
A.
Ask the lead developer to identify a solution, and then share the details with the team.
B.
Ask a technical manager or architect to determine a solution to the problem.
Answers
B.
Ask a technical manager or architect to determine a solution to the problem.
C.
Work with the product owner to add a spike to the next sprint to identify a solution.
Answers
C.
Work with the product owner to add a spike to the next sprint to identify a solution.
D.
Create a collaborative team environment so that the team can explore a solution together.
Answers
D.
Create a collaborative team environment so that the team can explore a solution together.
Suggested answer: D