Question 74 - PMI-ACP discussion

Report
Export

A team is delivering work as per the sprint plan, and team velocity is stabilized. However, at the end of the release, the customer is dissatisfied with project quality. What should the agile project manager have done to avoid this?

A.
Invited end customers to attend the stand ups
Answers
A.
Invited end customers to attend the stand ups
B.
Organized design review sessions with the customer to obtain sign-off
Answers
B.
Organized design review sessions with the customer to obtain sign-off
C.
Held regular meetings with the product owner and project team to elicit detailed business requirements
Answers
C.
Held regular meetings with the product owner and project team to elicit detailed business requirements
D.
Conducted frequent review meetings with the customer to continually enhance delivery effectiveness
Answers
D.
Conducted frequent review meetings with the customer to continually enhance delivery effectiveness
Suggested answer: D