A project sponsor is upset that an enhancement will be unavailable until next year. What should the product owner do?

A.
Accept responsibility for the product's delay.
Answers
A.
Accept responsibility for the product's delay.
B.
Ensure that the project sponsor's priorities are in the product backlog.
Answers
B.
Ensure that the project sponsor's priorities are in the product backlog.
C.
Negotiate with the project sponsor for increased funding.
Answers
C.
Negotiate with the project sponsor for increased funding.
D.
Empower the project sponsor to manage the product backlog.
Answers
D.
Empower the project sponsor to manage the product backlog.
Suggested answer: B