After completing the release plan, the team realizes that the project is very likely to have a negative ROI. What should the team do?
A.
Prioritize the backlog, and remove low-priority stories from the release plan to ensure a positive ROI.
B.
Replace some team members to reduce the release costs and minimize a negative ROI.
C.
Perform a root-cause analysis to remove waste from the delivery process and increase the ROI.
D.
Communicate the risk of a negative ROI to the stakeholders, and update the release plan.