During a sprint review, the product owner identifies a required improvement for a feature's user interface (Ul) delivered during the sprint. What should the product owner do next?

A.
Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer.
Answers
A.
Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer.
B.
Create a user story for this new improvement and prioritize it for the next sprint.
Answers
B.
Create a user story for this new improvement and prioritize it for the next sprint.
C.
Document it as a requirement creep.
Answers
C.
Document it as a requirement creep.
D.
Ask the team to take on additional story points to improve the Ul.
Answers
D.
Ask the team to take on additional story points to improve the Ul.
Suggested answer: A