An event management team is following an agile approach to prepare for an upcoming conference.

The regional sales manager, from where the conference is to be held, contacts the team with a number of questions about the company's booth.

What should the team do?

A.
Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.
Answers
A.
Inform the sponsor about the regional sales manager's disruptiveness and ask that all questions be diverted to the weekly meetings.
B.
Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.
Answers
B.
Stay focused on the current iteration and let the project manager deal with the regional sales manager's questions.
C.
Invite the regional sales manager to the next iteration review to share the progress.
Answers
C.
Invite the regional sales manager to the next iteration review to share the progress.
D.
Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.
Answers
D.
Create a risk on the risk register to account for some potentially new requirements from the regional sales manager.
Suggested answer: C