During a project's last few sprints, an agile practitioner notices an increase in defects. A root-cause analysis indicates that a poor understanding of the requirements was caused by the inability of the product owner to communicate clearly.

What should the agile practitioner do?

A.
Inform the product owner's manager so that corrective action may be taken.
Answers
A.
Inform the product owner's manager so that corrective action may be taken.
B.
Communicate this to the product owner, and offer to help facilitate discussions with the team.
Answers
B.
Communicate this to the product owner, and offer to help facilitate discussions with the team.
C.
Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.
Answers
C.
Encourage a team member to raise this during the retrospective to ensure that the product owner is aware.
D.
Escalate this issue to the sponsor so that corrective action may be taken.
Answers
D.
Escalate this issue to the sponsor so that corrective action may be taken.
Suggested answer: C