Question 82 - PMI-ACP discussion
An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity. What should the team do?
A.
Re-estimate the sprint's completed stories to increase and adjust the sprint's velocity.
B.
Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.
C.
Work with the product owner to create a spike with another agile team.
D.
Re-estimate the incomplete stories for the next sprint because its relative size has changed.