Question 97 - PMI-ACP discussion

Report
Export

Midway through a project, the product owner learns from the sponsor that a major component, which is already 20 percent complete, is unimportant to users. The component was part of the approved scope and a key selling point for the project.

What should the product owner do next?

A.
Obtain approval from the change control board to discontinue the component.
Answers
A.
Obtain approval from the change control board to discontinue the component.
B.
Ask the team to continue developing the component.
Answers
B.
Ask the team to continue developing the component.
C.
Ask the team to discontinue developing the component.
Answers
C.
Ask the team to discontinue developing the component.
D.
Request the sponsor's formal approval to discontinue the component.
Answers
D.
Request the sponsor's formal approval to discontinue the component.
Suggested answer: C