Question 98 - PMI-ACP discussion
While struggling to take ownership of delivery, an agile team fails to keep up with its sprint commitments. What should the agile coach do?
A.
Work with the sponsor to develop team expectations.
B.
Provide the customer with a list of deliverables and obtain agreement.
C.
Encourage the team to more frequently interact with all stakeholders.
D.
Work on finishing upfront product design rather than comprehensive documentation.