ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 105 - PMI-ACP discussion

Report
Export

During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.

What should the agile practitioner do?

A.
Work with the agile team and product owner to agree on the definition of done.
Answers
A.
Work with the agile team and product owner to agree on the definition of done.
B.
Ask the project sponsor to determine whether the product is completed.
Answers
B.
Ask the project sponsor to determine whether the product is completed.
C.
Plan another review after the product has been tested.
Answers
C.
Plan another review after the product has been tested.
D.
Add testing to the backlog, and have the product owner reprioritize.
Answers
D.
Add testing to the backlog, and have the product owner reprioritize.
Suggested answer: A
asked 23/09/2024
Jerin Cherian
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first