PMI PMI-ACP Practice Test - Questions Answers, Page 11
List of questions
Question 101

A project manager is concerned that the team has misaligned expectations with some stakeholders, and that user stories were written only from a generic user's perspective. This may lead the team to miss stories for non-generic users.
What agile tools can help the team address these issues?
Question 102

What can a team use to prioritize stories?
Question 103

A senior team member feels underutilized. What should the agile practitioner do?
Question 104

Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.
What should the team do?
Question 105

During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.
What should the agile practitioner do?
Question 106

A product owner obtains customer confirmation on product requirements and provides them to the team. After explaining the user stories, the product owner receives agreement for acceptance from the team.
What should the team do next?
Question 107

An agile team has only one database administrator with the necessary knowledge of databaserelated tasks. The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.
What should the agile coach do?
Question 108

A team working with a new technology faces a significant amount of uncertainty about its ability to deliver stories due to technical issues. What should the team do?
Question 109

A scrum master assumes a project that is essential to organizational growth. The project is expected to be in production for three years. What should the scrum master do first?
Question 110

A company is considering developing a new, complex application that will require a large initial investment. However, if successful, the profit potential is high. When preparing an analysis, what should be used to encourage stakeholders who are concerned about project failure to authorize the initial investment?
Question