List of questions
Related questions
Question 104 - PMI-ACP discussion
Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.
What should the team do?
A.
Plan for overtime, and include the effort as part of the estimation.
B.
Increase team velocity to deliver more story points.
C.
Identify the reason for over-commitment to the sprint and create an action plan for the following sprint.
D.
Add resources to assist with sprint execution.
Your answer:
0 comments
Sorted by
Leave a comment first