Question 129 - PMI-ACP discussion
A product owner complains that some of the requirements identified several Aerations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated What should the Scrum Master do?
A.
Point out that the team chose to work on other requirements to speed up the project
B.
Ensure that the product owner reviews the contents of the information radiator
C.
Ensure that the next sprint planning meeting reviews the satisfaction histogram
D.
Point out that it is the responsibility of the product owner to clarify requirements