A project Worn meets to estimate user stones for a sprint. While an important non-functional requirement must be delivered in the sprint the estimate exceeds sprint capacity.

What should the team do?

A.
Estimate only functional requirements that will impact product quality
Answers
A.
Estimate only functional requirements that will impact product quality
B.
Add learn resources
Answers
B.
Add learn resources
C.
Refer the issue to the product owner
Answers
C.
Refer the issue to the product owner
D.
Break non-functional requirements into those that can be delivered in the given sprint
Answers
D.
Break non-functional requirements into those that can be delivered in the given sprint
Suggested answer: C