During a mature agite team's planning meeting a team member proposes a new framework that would considerably reduce implementation lime However, the learn lacks the confidence to try the new framework To help the team gain confidence what should the agile practitioner suggest1

A.
Develop a spike
Answers
A.
Develop a spike
B.
Create an ishikawa diagram
Answers
B.
Create an ishikawa diagram
C.
Perform a pre-mortem analysis
Answers
C.
Perform a pre-mortem analysis
D.
Complete a variance and trend analysis
Answers
D.
Complete a variance and trend analysis
Suggested answer: A