Question 131

Report
Export
Collapse

On an agile project some of the development team is struggling to understand how the tasks and use stones fit into the overall product. How should this be addressed?

Review the iteration goals and have the team each describe the work to create shared understanding
Review the iteration goals and have the team each describe the work to create shared understanding
Create a story map for the minimal viable product (MVP) functionality
Create a story map for the minimal viable product (MVP) functionality
Capture this as a task in the retrospective and ensure there is more detail provided at the next planning session.
Capture this as a task in the retrospective and ensure there is more detail provided at the next planning session.
Have the product owner explain the product vision and review the release plan with the team
Have the product owner explain the product vision and review the release plan with the team
Suggested answer: B
asked 23/09/2024
Malik Khabir
34 questions

Question 132

Report
Export
Collapse

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted there is no value to the customers during this iteration What must the agile practitioner do?

Add the new change request as a new user story in the product backlog for the upcoming iteration
Add the new change request as a new user story in the product backlog for the upcoming iteration
Evaluate the impact of the change request and let the team and product owner decide and reprioritize based on value
Evaluate the impact of the change request and let the team and product owner decide and reprioritize based on value
Recommend cancelling the current iteration and plan the change request into the next iteration
Recommend cancelling the current iteration and plan the change request into the next iteration
Recommend that the product owner add this change request as a user story to me backlog tor the current aeration
Recommend that the product owner add this change request as a user story to me backlog tor the current aeration
Suggested answer: B
asked 23/09/2024
Aygul Korkmazlar
35 questions

Question 133

Report
Export
Collapse

The agile team disagrees with the business stakeholders on completing some epics. What could help eliminate misunderstandings?

Agree on requirements with all stakeholders
Agree on requirements with all stakeholders
Begin planning every tour iterations
Begin planning every tour iterations
Consider previous sprint demo feedback when planning the next sprint
Consider previous sprint demo feedback when planning the next sprint
Include the reasons for the project in the contract
Include the reasons for the project in the contract
Suggested answer: A
asked 23/09/2024
Carl James Carampot
39 questions

Question 134

Report
Export
Collapse

Why should a project team reduce the work in process?

It indicates poor project Quality
It indicates poor project Quality
It represents team members" utilization.
It represents team members" utilization.
It represents unrealized value
It represents unrealized value
It shows that the project is behind schedule
It shows that the project is behind schedule
Suggested answer: D
asked 23/09/2024
Gishi Anurag
30 questions

Question 135

Report
Export
Collapse

A learn member on a new scrum project previously provided support lo another application Due to issues with that application the team member's former supervisor continues assigning them tasks related to that protect The new project's scrum master includes this issue in the risk register.

What should the scrum master do next?

Monitor the threats and risks while allowing the team member to multitask on both projects
Monitor the threats and risks while allowing the team member to multitask on both projects
Assign more resources to the sprints to compensate for the absences of the team member
Assign more resources to the sprints to compensate for the absences of the team member
Ensure that the threats and risks are communicated and addressed
Ensure that the threats and risks are communicated and addressed
Assign fewer stones to the sprints so that the team member can still meet sprint goals
Assign fewer stones to the sprints so that the team member can still meet sprint goals
Suggested answer: C
asked 23/09/2024
Kimon Pope
32 questions

Question 136

Report
Export
Collapse

The product owner of a learn starts the iteration review with a quick walkthrough of the iteration goal, the list planned stones with status, and a demo of all the stones to the business. What should the product owner have done differently?

Demonstrated only the completed stones and seek stakeholder feedback
Demonstrated only the completed stones and seek stakeholder feedback
Presented the budget situation and review the cost variance
Presented the budget situation and review the cost variance
Reviewed the test results to gem confidence from the stakeholders
Reviewed the test results to gem confidence from the stakeholders
Presented a demo of all the stories including the work in progress stones
Presented a demo of all the stories including the work in progress stones
Suggested answer: A
asked 23/09/2024
Moraes, Jefferson
45 questions

Question 137

Report
Export
Collapse

An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?

Regularly circulate an updated, detailed version of the project plan
Regularly circulate an updated, detailed version of the project plan
Frequently update the online project management office (PMO) repository site
Frequently update the online project management office (PMO) repository site
invite the stakeholders to daily stand ups
invite the stakeholders to daily stand ups
Post a project board in an area where all can view it.
Post a project board in an area where all can view it.
Suggested answer: D
asked 23/09/2024
Henny Smit
36 questions

Question 138

Report
Export
Collapse

A learn member 15 stressed due to a heavy workload, while other team members have some slack in their schedules How should the learn lead address this?

inform management, and suggest that additional resources may be required
inform management, and suggest that additional resources may be required
Discuss me issue with the learn m me daily stand up meetings
Discuss me issue with the learn m me daily stand up meetings
Meet personally with the stressed learn member to brainstorm ways to better manage their lime
Meet personally with the stressed learn member to brainstorm ways to better manage their lime
Begin tracking the stressed learn member's tastes in a separate backlog for additional analysis and reporting
Begin tracking the stressed learn member's tastes in a separate backlog for additional analysis and reporting
Suggested answer: C
asked 23/09/2024
Carmina Medel
33 questions

Question 139

Report
Export
Collapse

During a mature agite team's planning meeting a team member proposes a new framework that would considerably reduce implementation lime However, the learn lacks the confidence to try the new framework To help the team gain confidence what should the agile practitioner suggest1

Develop a spike
Develop a spike
Create an ishikawa diagram
Create an ishikawa diagram
Perform a pre-mortem analysis
Perform a pre-mortem analysis
Complete a variance and trend analysis
Complete a variance and trend analysis
Suggested answer: A
asked 23/09/2024
Myratgeldi Bekdurdyyev
46 questions

Question 140

Report
Export
Collapse

Midway through a sprint. a scrum team member advises the team of a new requirement Dial may change the initial scope What should the team do?

Work on requirements that (he product owner may have overlooked
Work on requirements that (he product owner may have overlooked
Record the scope creep m the change management tog
Record the scope creep m the change management tog
Add the new requirement to the product backlog
Add the new requirement to the product backlog
Ask the scrum master to secure additional time and resources
Ask the scrum master to secure additional time and resources
Suggested answer: D