Question 131

Report Export Collapse

On an agile project some of the development team is struggling to understand how the tasks and use stones fit into the overall product. How should this be addressed?

Become a Premium Member for full access
  Unlock Premium Member

Question 132

Report Export Collapse

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted there is no value to the customers during this iteration What must the agile practitioner do?

Become a Premium Member for full access
  Unlock Premium Member

Question 133

Report Export Collapse

The agile team disagrees with the business stakeholders on completing some epics. What could help eliminate misunderstandings?

Become a Premium Member for full access
  Unlock Premium Member

Question 134

Report Export Collapse

Why should a project team reduce the work in process?

Become a Premium Member for full access
  Unlock Premium Member

Question 135

Report Export Collapse

A learn member on a new scrum project previously provided support lo another application Due to issues with that application the team member's former supervisor continues assigning them tasks related to that protect The new project's scrum master includes this issue in the risk register.

What should the scrum master do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 136

Report Export Collapse

The product owner of a learn starts the iteration review with a quick walkthrough of the iteration goal, the list planned stones with status, and a demo of all the stones to the business. What should the product owner have done differently?

Become a Premium Member for full access
  Unlock Premium Member

Question 137

Report Export Collapse

An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?

Become a Premium Member for full access
  Unlock Premium Member

Question 138

Report Export Collapse

A learn member 15 stressed due to a heavy workload, while other team members have some slack in their schedules How should the learn lead address this?

Become a Premium Member for full access
  Unlock Premium Member

Question 139

Report Export Collapse

During a mature agite team's planning meeting a team member proposes a new framework that would considerably reduce implementation lime However, the learn lacks the confidence to try the new framework To help the team gain confidence what should the agile practitioner suggest1

Become a Premium Member for full access
  Unlock Premium Member

Question 140

Report Export Collapse

Midway through a sprint. a scrum team member advises the team of a new requirement Dial may change the initial scope What should the team do?

Become a Premium Member for full access
  Unlock Premium Member