PMI PMI-ACP Practice Test - Questions Answers, Page 14

List of questions
Question 131

On an agile project some of the development team is struggling to understand how the tasks and use stones fit into the overall product. How should this be addressed?
Question 132

The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope Unless this change is accepted there is no value to the customers during this iteration What must the agile practitioner do?
Question 133

The agile team disagrees with the business stakeholders on completing some epics. What could help eliminate misunderstandings?
Question 134

Why should a project team reduce the work in process?
Question 135

A learn member on a new scrum project previously provided support lo another application Due to issues with that application the team member's former supervisor continues assigning them tasks related to that protect The new project's scrum master includes this issue in the risk register.
What should the scrum master do next?
Question 136

The product owner of a learn starts the iteration review with a quick walkthrough of the iteration goal, the list planned stones with status, and a demo of all the stones to the business. What should the product owner have done differently?
Question 137

An agile practitioner wants to ensure that stakeholders have current information about a project's progress What should the agile practitioner do?
Question 138

A learn member 15 stressed due to a heavy workload, while other team members have some slack in their schedules How should the learn lead address this?
Question 139

During a mature agite team's planning meeting a team member proposes a new framework that would considerably reduce implementation lime However, the learn lacks the confidence to try the new framework To help the team gain confidence what should the agile practitioner suggest1
Question 140

Midway through a sprint. a scrum team member advises the team of a new requirement Dial may change the initial scope What should the team do?
Question