During a retrospective the agile practitioner discovers that a team member's process improvement idea has worsened the outcome What should the agile practitioner do?
A.
Commend the team on A. trying the idea then encourage discussion regarding alternatives
B.
Ask a manager to direct the team on fixing the process
C.
Encourage the team to continue executing the idea to see if it improves
D.
Privately speak with the learn member to convey that their idea worsened the outcome