Question 143 - PMI-ACP discussion
A project is starling and the type of wont is complex and suitable for agile in assessing the learn members it appears that co-location would be a challenge.
What should the agile practitioner do?
A.
Select and implement collaboration tools to augment team interactions
B.
Provide each geographical area with their own product owner and divide the work between the teams
C.
increase the number of requirements documents and ensure they are dearly communicated
D.
After several sprints calcuate velocity based on primary learn location and use secondary team as reserve
Your answer: