Midway through an iteration, an agile learn learns that a team member will be unavailable for the next two iterations As a high-performance team what should the team do?

A.
Raise an impediment that resource tasks will be blocked, and notify the product owner
Answers
A.
Raise an impediment that resource tasks will be blocked, and notify the product owner
B.
Ask the delivery manager tor a temporary resource
Answers
B.
Ask the delivery manager tor a temporary resource
C.
Ask the scrum master to assign that team member's tasks to the next available resource
Answers
C.
Ask the scrum master to assign that team member's tasks to the next available resource
D.
Assume the team member's tasks to meet iteration goals, and notify the product owner.
Answers
D.
Assume the team member's tasks to meet iteration goals, and notify the product owner.
Suggested answer: A