An agile coach realizes that a team responsible for a major release is a few months behind schedule The marketing department is unaware of this delay and is planning to start the marketing campaign and announce the release What should the agile coach do?

A.
Meet with the agile team lead to discuss ways to improve team velocity and get back on track.
Answers
A.
Meet with the agile team lead to discuss ways to improve team velocity and get back on track.
B.
Use this as a learning opportunity and allow the team to hand* the situation when the marketing campaign begins.
Answers
B.
Use this as a learning opportunity and allow the team to hand* the situation when the marketing campaign begins.
C.
In the upcoming retrospective, discuss ways to improve sharing protect status information.
Answers
C.
In the upcoming retrospective, discuss ways to improve sharing protect status information.
D.
Meet with the marketing stakeholders to explain that the team will miss the planned release date.
Answers
D.
Meet with the marketing stakeholders to explain that the team will miss the planned release date.
Suggested answer: A