Early in a project stakeholder analysts is performed, however an organizational restructure redefines key rotes What should the protect team do?

A.
Note the changes to the restructure and roles that affect team activities
Answers
A.
Note the changes to the restructure and roles that affect team activities
B.
Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements
Answers
B.
Use direct engagement and two-way conversation to update the stakeholder analysis for any new stakeholder requirements
C.
Email a copy of the protect vision to nose redefined for key roles and ask if they need to be involved in the project
Answers
C.
Email a copy of the protect vision to nose redefined for key roles and ask if they need to be involved in the project
D.
Obtain a copy of the redefined key roles to update the stakeholder analysis
Answers
D.
Obtain a copy of the redefined key roles to update the stakeholder analysis
Suggested answer: B