Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this What should the agile practitioner do?

A.
Jointly meet with the team and product owner to discuss options and determine the end date
Answers
A.
Jointly meet with the team and product owner to discuss options and determine the end date
B.
Announce that the team has exceeded the predicted velocity and that the end date will be earner than planned
Answers
B.
Announce that the team has exceeded the predicted velocity and that the end date will be earner than planned
C.
Ask the product owner to include additional features in the product backlog then replay subsequent iterations
Answers
C.
Ask the product owner to include additional features in the product backlog then replay subsequent iterations
D.
Ask the team to decrease velocity to meet contractual obligations and document this decision
Answers
D.
Ask the team to decrease velocity to meet contractual obligations and document this decision
Suggested answer: A