Question 157 - PMI-ACP discussion
During its first sprint a new scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories. What should the team do?
A.
Cross-tram some members in the automation framework to broaden their capacity with that skill
B.
Ask the product owner to add team members to boost this particular skill set
C.
Send a member to automation framework training when funds are available
D.
Avoid using test automation by swarming on the testing tasks and using manual testing