Question 168 - PMI-ACP discussion
An experienced product owner presents the epics and corresponding stones during a release planning session with the established team The executive sponsor asks the team when the features will he delivered What should the agile team do?
A.
Evaluate how much can be delivered based on the Scrum Master's estimation
B.
identify a set of user stored based on the team's velocity
C.
initiate an estimation session
D.
Consult historical data for project completion