Question 167 - PMI-ACP discussion
A legal department representative contacts the scrum master because white the projects budget has been maintained it has exceeded its original contracted time and scope. What should the scrum master do?
A.
Meet with the team to gam alignment with the legal department's need to stay within the contracted time and scope
B.
Work with the customer to narrow me scope
C.
Share the project's trajectory with the legal department
D.
Meet with the legal department to help them understand that the customer and the team are satisfied with the time and deliverables