Outing planning for the next iteration an agile team identifies most of the story points that are expected to be delivered. How should an agile practitioner work with the team to help identity the iteration's remaining scope?

A.
Convince the learn to stop planning and keep the size small
Answers
A.
Convince the learn to stop planning and keep the size small
B.
identify the technically minimal and achievable tasks
Answers
B.
identify the technically minimal and achievable tasks
C.
Refer to the remaining prioritized backlog items
Answers
C.
Refer to the remaining prioritized backlog items
D.
Select some of the smallest items from the backlog
Answers
D.
Select some of the smallest items from the backlog
Suggested answer: C