What can an agile team use to prioritize stones?

A.
Planning poke' technique
Answers
A.
Planning poke' technique
B.
Weighted average calculation
Answers
B.
Weighted average calculation
C.
Risk-value quadrant
Answers
C.
Risk-value quadrant
D.
INVEST scale
Answers
D.
INVEST scale
Suggested answer: C