Question 174 - PMI-ACP discussion
A technical problem arises that win likely impact the stories planned for delivery in the current sprint What should the scrum master do?
A.
Consider adding a story to the next sprint to seek resolution
B.
immediately solve the problem on behalf of the team
C.
Ask the team to collaboratively work out a solution
D.
Engage a technical manager to assist With finding a solution