A technical problem arises that win likely impact the stories planned for delivery in the current sprint What should the scrum master do?

A.
Consider adding a story to the next sprint to seek resolution
Answers
A.
Consider adding a story to the next sprint to seek resolution
B.
immediately solve the problem on behalf of the team
Answers
B.
immediately solve the problem on behalf of the team
C.
Ask the team to collaboratively work out a solution
Answers
C.
Ask the team to collaboratively work out a solution
D.
Engage a technical manager to assist With finding a solution
Answers
D.
Engage a technical manager to assist With finding a solution
Suggested answer: C