What should a Scrum Master do when one team member falls behind in their tasks'?

A.
Move the task to another team member who has spare capacity in the sprint
A.
Move the task to another team member who has spare capacity in the sprint
Answers
B.
Ask the team for suggestions
B.
Ask the team for suggestions
Answers
C.
Privately offer the team member encouragement to meet task commitments
C.
Privately offer the team member encouragement to meet task commitments
Answers
D.
Notify the product owner
D.
Notify the product owner
Answers
Suggested answer: B

A company has decided to combine Iwo similar products consisting of multiple teams into one product Engaged customers want to know how the company is looking at re-organizing it's teams.

What strategy should be employed to re-organize the teams?

A.
All the teams from both products should be simultaneously called together and allowed to completely self-manage
A.
All the teams from both products should be simultaneously called together and allowed to completely self-manage
Answers
B.
Teams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies
B.
Teams that worked on similar components in the separate products should be combined to minimize disruption and capitalize on synergies
Answers
C.
After grouping individuals by role multi-discipline teams should be created that are comprised of one member from each role
C.
After grouping individuals by role multi-discipline teams should be created that are comprised of one member from each role
Answers
D.
Features should be prioritized and then teams should be orgainzed around those priorities
D.
Features should be prioritized and then teams should be orgainzed around those priorities
Answers
Suggested answer: A

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

A.
Finalize the feedback in the form of a change request
A.
Finalize the feedback in the form of a change request
Answers
B.
Limit the scope of the feedback to only those changes that the team can feasibly accommodate
B.
Limit the scope of the feedback to only those changes that the team can feasibly accommodate
Answers
C.
Encourage all feedback, then work with the customer to prioritize work for future sprints
C.
Encourage all feedback, then work with the customer to prioritize work for future sprints
Answers
D.
Allow the team to decide what feedback to incorporate.
D.
Allow the team to decide what feedback to incorporate.
Answers
Suggested answer: C

A team member has spent 5 days on a spike and the first set of experiments has not been successful The issue is the development team member has determined a short-term rather than a long-term solution.

What should the project leader do?

A.
Assign the spike to another resource to continue research for the long-term solution
A.
Assign the spike to another resource to continue research for the long-term solution
Answers
B.
Re-establish the spike, encourage experimentation and collaborate with the team.
B.
Re-establish the spike, encourage experimentation and collaborate with the team.
Answers
C.
Stop experimentation and negotiate the short-term solution with the customer.
C.
Stop experimentation and negotiate the short-term solution with the customer.
Answers
D.
Schedule a root-cause analysis with the development team on the mam issues with the spike
D.
Schedule a root-cause analysis with the development team on the mam issues with the spike
Answers
Suggested answer: B

An organization highly values security However, a team member on a project has found a way to save time and money with less robust security features. What should the team member do?

A.
Influence the customer
A.
Influence the customer
Answers
B.
Mention the idea at the next retrospective
B.
Mention the idea at the next retrospective
Answers
C.
Show the customer how much time and money would be saved.
C.
Show the customer how much time and money would be saved.
Answers
D.
Present the idea at the next ceremony attended by stakeholders to obtain their input
D.
Present the idea at the next ceremony attended by stakeholders to obtain their input
Answers
Suggested answer: D

The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach What should the agile practitioner do?

A.
Ask the opinion of key stakeholders and the client to ensure the correct approach is being used
A.
Ask the opinion of key stakeholders and the client to ensure the correct approach is being used
Answers
B.
Work with the team to use this approach and request a quality assurance iteration after every three iterations
B.
Work with the team to use this approach and request a quality assurance iteration after every three iterations
Answers
C.
Propose to completely eliminate test automation, since this is a quality assurance function
C.
Propose to completely eliminate test automation, since this is a quality assurance function
Answers
D.
Suggest merging the quality assurance and delivery teams to enhance each iteration's testautomation levels and reduce redundancy
D.
Suggest merging the quality assurance and delivery teams to enhance each iteration's testautomation levels and reduce redundancy
Answers
Suggested answer: D

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents How should the agile practitioner address this concern?

A.
Educate the QA manager that in agile, quality is integrated from the begining to end of the project.
A.
Educate the QA manager that in agile, quality is integrated from the begining to end of the project.
Answers
B.
Write backlog items that include QA as part of the description.
B.
Write backlog items that include QA as part of the description.
Answers
C.
Ask for the current QA documents and incorporate them into the technical debt backlog.
C.
Ask for the current QA documents and incorporate them into the technical debt backlog.
Answers
D.
Ask the product owner to write tests and QA controls into the acceptance criteria
D.
Ask the product owner to write tests and QA controls into the acceptance criteria
Answers
Suggested answer: A

An agile project leader notices that the team's velocity has decreased. In examining data provided by team members, the project leader discovers that one team member has been slow to enter story statuses.

What can happen as a result'

A.
The team will be unable to understand the iteration's status
A.
The team will be unable to understand the iteration's status
Answers
B.
The team will be unable to judge the project design's validity.
B.
The team will be unable to judge the project design's validity.
Answers
C.
The team cannot give accurate updates to management
C.
The team cannot give accurate updates to management
Answers
D.
Team collaboration cannot be measured effectively
D.
Team collaboration cannot be measured effectively
Answers
Suggested answer: A

A client slates that a product is not being built as requested. How should the agile team address this?

A.
Conduct an internal review to validate functionality before shipping
A.
Conduct an internal review to validate functionality before shipping
Answers
B.
Audit the quality control process to ensure that the product adheres to requirements.
B.
Audit the quality control process to ensure that the product adheres to requirements.
Answers
C.
Lengthen iterations to ensure there is sufficient time to build functionality
C.
Lengthen iterations to ensure there is sufficient time to build functionality
Answers
D.
Hold product review sessions with the client to obtain product acceptance.
D.
Hold product review sessions with the client to obtain product acceptance.
Answers
Suggested answer: B

When prioritizing features to be delivered in an iteration, on what features should an agile team defer work?

A.
High-risk and high-value
A.
High-risk and high-value
Answers
B.
High-risk and low-value
B.
High-risk and low-value
Answers
C.
Low-risk and low-value
C.
Low-risk and low-value
Answers
D.
Low-risk and high-value
D.
Low-risk and high-value
Answers
Suggested answer: B