Question 185 - PMI-ACP discussion
A projects first iteration contains item
A.
and its second iteration contains item B. The first iteration is behind schedule which will impact the second iteration Since items A and B are similar a team member suggests beginning the design of item B. What should the agile practitioner do?
B.
Defer starting the design of item B until the second iteration is being planned
C.
Proceed with the design of item B, since it will hasten the second iteration
D.
Escalate the issue to me customer and obtain their approval before starting the design of item B
E.
Log the issue in the risk register and request change control board (CCB) approval