A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete m the marketplace1. What analysis should the team use to understand the issues?
A.
Risk management
B.
Variance and trend
C.
Kano model
D.
Fishbone diagram