Question 194 - PMI-ACP discussion
A team member has spent 5 days on a spike and the first set of experiments has not been successful The issue is the development team member has determined a short-term rather than a long-term solution.
What should the project leader do?
A.
Assign the spike to another resource to continue research for the long-term solution
B.
Re-establish the spike, encourage experimentation and collaborate with the team.
C.
Stop experimentation and negotiate the short-term solution with the customer.
D.
Schedule a root-cause analysis with the development team on the mam issues with the spike
Your answer: