Which is one of the three levels of plan in PRINCE2?

A.
Benefits Review Plan
Answers
A.
Benefits Review Plan
B.
Programme Plan
Answers
B.
Programme Plan
C.
Team Plan
Answers
C.
Team Plan
D.
Project Brief
Answers
D.
Project Brief
Suggested answer: C

Explanation:

PRINCE2 defines three levels of planning: Project Plan, Stage Plan, and Team Plan. The Team Plan is one of these three levels, specifically designed to manage the delivery of the work packages assigned to the team within a management stage.

Reference: PRINCE2 Foundation official documentation and study materials.