What theme estimates the cost of delivering the project?

A.
Business Case
Answers
A.
Business Case
B.
Change
Answers
B.
Change
C.
Plans
Answers
C.
Plans
D.
Progress
Answers
D.
Progress
Suggested answer: C

Explanation:

The Plans theme in PRINCE2 is responsible for estimating the cost of delivering the project. This theme involves the development of plans that outline how, when, and by whom the project's objectives are to be achieved, including the necessary resources and associated costs.

Reference: PRINCE2 Foundation official documentation and study materials.