Which of the following statements about lines of authority and reporting are true?

1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.

2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

A.
Only 1 is true
Answers
A.
Only 1 is true
B.
Only 2 is true
Answers
B.
Only 2 is true
C.
Both 1 and 2 are true
Answers
C.
Both 1 and 2 are true
D.
Neither 1 or 2 are true
Answers
D.
Neither 1 or 2 are true
Suggested answer: C

Explanation:

Both statements are true within the PRINCE2 framework. Statement 1 is accurate as the Project Manager does have day-to-day control within the limits set by the Project Board for a management stage. Statement 2 is also correct because if a Team Manager forecasts a deviation beyond Work Package tolerances, it should indeed be referred to the Project Manager.

Reference: PRINCE2 Foundation official study materials.