What theme provides all management levels within the project management team with mechanisms for monitoring and control?

A.
Progress
Answers
A.
Progress
B.
Change
Answers
B.
Change
C.
Organization
Answers
C.
Organization
D.
Quality
Answers
D.
Quality
Suggested answer: A

Explanation:

The Progress theme in PRINCE2 provides all management levels within the project management team with mechanisms for monitoring and control. It involves tracking the ongoing viability of the plans and the project's objectives, and it includes mechanisms for reporting, reviewing, and ensuring that decisions on continued investment are based on accurate information.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources