Which product records any project outcomes perceived as negative by stakeholders?

A.
Business Case
Answers
A.
Business Case
B.
Project Plan
Answers
B.
Project Plan
C.
Communication Management Strategy
Answers
C.
Communication Management Strategy
D.
Project Product Description
Answers
D.
Project Product Description
Suggested answer: C

Explanation:

In PRINCE2, the Communication Management Strategy is the document that outlines how project communications should be managed. It includes how information will be disseminated amongst stakeholders and how feedback will be collected. Negative outcomes perceived by stakeholders are typically recorded as part of the feedback mechanism defined in the Communication Management Strategy.

Reference: PRINCE2 Foundation official guide and study material.